Prior to 11/8, reports were weekly.
Design
- Checkout on track for mid-May
- We have made significant progress on "taming" shipping and handling preferences.
LOAP:
Launched 3/24.
Launch:
- CHANGE - 8/15 (+ 1 weekday, essentially unchanged)
LOAP:
Launch is imminent - need to address Twitter feed and put finishing touches on content.
Launch:
- CHANGE - 7/18 > 8/14 (+ 19 weekdays)
Meeting - Invited Jeff B and John D to present on "The Experience"
Issues & highlights:
Bulk of LOAP coding complete. Good progress on saving items and tagging, but design likely to take longer than budgeted in WorkZone to complete. No impact yet on launch date. Upcoming activities light, due to school vacation week.
Working launch date: 7/18/13
Change since last report: None.
Issues & highlights:
CE functionality that needs to be preserved is relatively complex. Providing a seamless flow between Avante and Web tasks presents some technical and UI challenges; more discovery is required.
Working launch date: 7/5/13
Change since last report: None.
Issues & highlights:
On track for scaled back launch scenario
Working launch date: July 4, 2013
Change since last report: -10 weeks
Issues & highlights:
- Revised project plan and launch date
- Personas & scenarios
- YMAC design in progress
Working launch date: September 9, 2013
Change since last report: +63 days
Issues & highlights:
- Competing priorities/work causing programmers and marketing to have uncertainty around dates and/or push dates out for some tasks/milestones.
- Should we meet next Thurs., 11/15? Next reporting period includes 11/22 & 23 holiday.
Working launch date: to be posted Friday
Change since last report: +N days or - N days or no change
Issues & highlights
- Programming shop widget pushed to 11/30. Work to commence on search results at that point; at some point after that commences, developers will need YMAC requirements, which until this week has been stalled - level of effort to complete that will not be known till next week. In spite of this, no change to working launch date based on current dependencies.
- If we meet our goals for My Account/User prefs by 11/2, we'll likely want to have a design review with Ladd & Dawn soon thereafter.
Working launch date: July 8, 2013
Change since last report: No change
Issues & concerns
My account/user prefs pushed out at least one week. Steve B. starts Mon., 10/22.
Working launch date: July 8, 2013
Change since last report: +10 days
Issues & concerns
Some activities that were planned for this week had to be deferred to next week, due to competing priorities for Sales & Marketing (e.g. pricing) and unforeseen technical hurdles for programmers.
Working launch date: June 28, 2013
Change since last report: no change