The following programs need to have Atlanta (whs 02) added as a production plant. Please put these program changes onto a separate task because they will need to be rolled to LIVE mid-March (before we go live with the new site).
As a guide, you can follow the logic for task 100987 that you will see in these programs. That's the task that I used to add Reno when they became a production facility.
- SSMS9007.1 (bottomseal table PREFX = "BG", sideweld table PREFX = "SWG", singlewound sheeting table PREFX = "SWSG"
- SSMS9008.1 req'd add'l change to lower width from 54" down to 50" for manipulator lines because of Atlanta line 6 - I made this change and added GA06 to PROD.BARCODE.LAD<4> in DEV/LIVE (Judy) I also changed logic that forces SW 1-up (same logic as for Dallas)
- SFCS9004.1 (awaiting info from Cathy to see what printer names will be added to SYSCON PROD.PRINTER.LAD fields 12/13)
- SOPS9085.1
- SOPS9097.3 (PLANT.NAME = "GA"; COST.TABLE = "S2")
- SOPS9148.1
- QUOS4000.4PS
- QUOS9008.1