Agenda for 4/16
1-Status of design tasks
- Past orders, had marked complete but Ladd's changes pushed completion of specs/documentation to 4/16.
- Upcoming - Have lots of direction on Checkout to work through, and more requirements gathering with CE; so far still on track for 5/14 (note, SB on vacation 4/29-5/3).
2-Status of programming tasks
- Past orders, due 4/10 - let's revise date based on design changes, also determine what parts (e.g. invoices?) are outside of scope for initial launch. (If it can all be done w/out pushing dates out, great, but anything outside of scope that pushes dates out should be deferred.)
- Search results, YMAC, product descriptions due 4/15. Revise?
- Need product description content from marketing? Status? (Owen/Cliff)
3-Discussion: Are there any major chunks of programming or design or other work that are unaccounted for in WorkZone and need to be in place for launch?
For example
- Reworking Avante CE Request System to link up with w/web interface all transactions moving out of Avante
- Data conversion/migration
- Web analytics and metrics
- Notifications, new and existing
- The Experience - I hope that this is still considered a post launch feature, based on our earlier rescoping. John D and Jeff slated to present another iteration next week. Hopefully we will know more about what it would take to implement.