Laddawn.com : Blog post template

Meeting 11/29: Ladd, Dawn, Owen, Jim, John, Steve

Issues & highlights:
Working launch date: September 9, 2013

Change since last report: +63 days   

General  
Application Requirements & Design
Programming
Content
QA
Rollout & Communication
Status & accomplishments

New .Net developer, Sal starts 12/10

Interviewing Avante candidate  Thursday 11/28

YMAC, due 11/30 - Critical mass of results logic completed; loose ends can be addressed during programming. Design proving more challenging. Date needs to be pushed 1-2 weeks - no impact on launch date (yet).

Created user personas with input from CE.

Narrative thread-Held kickoff meeting to delegate narrative thread to Jeff Bercume, Chris Pagoaga, and John Dower (tentatively due 3/1/13)
 

Shop widget, due 11/30 - Anticipate having Shop widget complete for bags only. Back-end programming will likely take a few more weeks. No impact on launch date (yet).

Go thru As-Is and To-Be content inventories, due 11/30. Date pushed to 12/31 - no impact on launch date (yet).

 

Scheduled to commence 3/14/13Planning scheduled to commence 1/17/13
Upcoming activities & goals
 

Complete YMAC results design

Product descriptions (due 12/7)



Commence work on next programming task: search results (due 3/12/13)

 

 

N/AN/A
Gantt Chart

WorkZone now reflects:

  • More realistic estimates of duration of key design and programming tasks
  • The addition of a new developer (Sal) in early Dec. and splitting programming into two parallel tracks.

As a result, the new working launch date is Sept. 9. 

Collapsed quarterly view

To be posted Thurs morning

 

Expanded monthly view

To be posted Thurs morning